exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 6 discussion

Actual exam question from PMI's PMI-RMP
Question #: 6
Topic #: 1
[All PMI-RMP Questions]

The stakeholder is unwilling to make decisions that would result in negative consequences to the project. Which of the following describes the stakeholder's attitude regarding project risks?

  • A. Risk averse
  • B. Risk neutral
  • C. Risk accepting
  • D. Not enough information available to describe the stakeholder's risk attitude
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Linkedin_Dario_Conde
6 months, 2 weeks ago
Selected Answer: A
A is correct "He is unwilling"
upvoted 1 times
...
Linkedin_Dario_Conde
6 months, 2 weeks ago
Selected Answer: A
A is correct as he is unwilling
upvoted 1 times
...
Azharmak
6 months, 2 weeks ago
Cannot take any risk. A
upvoted 1 times
...
aws_guru1
1 year, 3 months ago
A. Risk averse
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...