Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Exam PMP topic 1 question 369 discussion

Actual exam question from PMI's PMP
Question #: 369
Topic #: 1
[All PMP Questions]

After the project charter's approval, the project manager needs to work on detailed project requirements, constraints, and assumptions with stakeholders.
However, not all of the stakeholders are immediately available for a meeting in the short term.
What should the project manager do in order to gather the information needed from stakeholders?

  • A. Conduct a meeting to build the project management plan with the stakeholders who are available.
  • B. Email, call, or meet with each stakeholder separately to obtain their input.
  • C. Escalate to the project sponsor that not all stakeholders are available for a meeting.
  • D. Meet with the project management team to build the project management plan before consulting stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Yuuns
1 day, 1 hour ago
D does not achieve what is asked by the question.
upvoted 1 times
...
Trytrio
2 weeks ago
Selected Answer: D
D should be right
upvoted 1 times
...
Kesavaperumal
1 month ago
I thought D is right answer
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...