Exam PMP topic 1 question 105 discussion

Actual exam question from PMI's PMP
Question #: 105
Topic #: 1
[All PMP Questions]

A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the importance of the project meeting the company's strategy, investment, and compliance requirements.
What should the project manager do?

  • A. Put into place a project governance model in line with the requirements
  • B. Replicate the organizational governance to the project governance
  • C. Create an organizational project management governance
  • D. Ask the organization to create a project portfolio governance
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
4f6ae44
2 weeks, 4 days ago
A is the correct Answer The PM got some direction from the Sponsor and with that he can at least establish a Governance Model for the project to begin with. Remember he can at least control within his capacity around his project but can't do Option "C" as it is at the org level. "D" is shying away from his responsibilities so "A" is the best choice among all these.
upvoted 1 times
...
odylec
3 months, 2 weeks ago
Selected Answer: B
B is the answer. All the companies have a governance so you must follow this for your project.Its not necessary to start from the begin.
upvoted 1 times
...
Akshay_Kumar82
5 months ago
i also think A is wrong. Has PM enough power to put the governance model in place?
upvoted 1 times
...
mesacgon
6 months, 1 week ago
A. parece lo más básico ya que no especifica que tipo de empresa es, se asume que es una empresa más funcional o sencilla por lo cual el PM no tiene tanta fuerza para imponer gobernanza y se debería limitar solo al alcance del proyecto creo yo.
upvoted 1 times
...
Tracyyy123
6 months, 3 weeks ago
Selected Answer: A
A correct
upvoted 1 times
...
Lucky_Cindy
7 months, 2 weeks ago
Selected Answer: A
A is correct
upvoted 1 times
...
Goku_PMP
8 months, 3 weeks ago
Selected Answer: B
B , the only best thing he can do, to use organisation governance.
upvoted 1 times
amicu
4 months ago
But the problem is a company without a project management governance structure. So, where we can copy?
upvoted 1 times
...
...
victory108
11 months, 2 weeks ago
Selected Answer: A
A. Put into place a project governance model in line with the requirements
upvoted 1 times
...
AP2023S
11 months, 2 weeks ago
Selected Answer: A
Ok... "A" seems to be the best solution...but does it make sense? In a company, is the PM who put the governance model in place? Has him enough power to do it?
upvoted 1 times
...
RagazzoAlex
1 year, 2 months ago
Selected Answer: A
looks the best option
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.