Question #: 110
Topic #: 1
[All PMP Questions]

A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict schedule and budget, and the project manager is concerned about their ability to deliver it.
What should the project manager do?

  • A. Engage the agile resources through video conferencing on a daily basis
  • B. Advise the sponsor that the project will be delayed as agile training will be required
  • C. Request a budget extension to get local resources experienced in agile
  • D. Plan to have the agile resources temporarily relocate to the project manager's location
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Princessviv96
1 month ago
Selected Answer: A
In my opinion I feel engaging the agile resource over video conferencing will help as it will bridge the distance and is a practical low cost option however, if it fails Advise the sponsor that the project will be delayed as agile training will be required.
upvoted 1 times
...
nohaph
5 months, 1 week ago
Selected Answer: A
I choose A. co-location is often preferred in agile methodologies to enhance communication and collaboration. However, given the strict schedule and budget constraints, relocating the agile resources might not be feasible. While co-location can be ideal, daily video conferencing can still effectively bridge the gap. It allows for real-time communication, quick feedback loops, and maintaining team cohesion without the additional costs and logistical challenges of relocation.
upvoted 1 times
...
43a41d4
6 months, 3 weeks ago
Selected Answer: A
Schedule and budget are main constraints. So "B,C and D" can't be applied. A is the best answer in this scenario.
upvoted 1 times
...
martinx84
10 months, 3 weeks ago
Selected Answer: A
Engage the agile resource
upvoted 1 times
...
KennethTang
1 year, 3 months ago
Selected Answer: D
In agile, co-location would be considered first, so I choose D
upvoted 2 times
...
Tuanit
1 year, 7 months ago
Selected Answer: A
A is the first worthy action to take.
upvoted 1 times
...
Lucky_Cindy
1 year, 7 months ago
Selected Answer: A
A is the most close answer
upvoted 1 times
...
Goku_PMP
1 year, 8 months ago
Selected Answer: D
in Agile, colocation is best possible solution.
upvoted 1 times
...
TomGrey
1 year, 10 months ago
Selected Answer: A
A is the answer
upvoted 1 times
...
victory108
1 year, 11 months ago
Selected Answer: A
A. Engage the agile resources through video conferencing on a daily basis
upvoted 1 times
...
Hung3102
2 years, 1 month ago
A is answer
upvoted 2 times
...
JENLT
2 years, 2 months ago
Selected Answer: B
In the real world, advise or notify project sponsors on potential delay sounds like the best approach
upvoted 1 times
Jamrock
1 year, 10 months ago
In the real world you would be walked out the door if you came to the Sponsor, of all people, with that nonsense.
upvoted 3 times
Hashi1_snr
1 year, 6 months ago
You got me cracking loud and it's indeed a nonsense thing to do. The chosen answer is the correct choice to do. Lol
upvoted 1 times
...
...
wzjh2008
2 years, 2 months ago
But they have strict schedule… so A should be the best option
upvoted 5 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago