exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 445 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 445
Topic #: 1
[All PRINCE2-Foundation Questions]

Which process is used by the project board to respond to an exception report?

  • A. Controlling a stage
  • B. Managing a stage boundary
  • C. Managing product delivery
  • D. Directing a project
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Examcollectorthanos
2 weeks, 1 day ago
B is correct; Why other options are not suitable: A. Controlling a stage: This process is about the project manager's activities within a stage, not the project board's response to exceptions. C. Managing product delivery: This focuses on the creation of products, not on handling exceptions. D. Directing a project: This is about the project board's overall direction and decision-making, but the specific process for handling exceptions is "managing a stage boundary."
upvoted 1 times
...
Kjennset
1 month ago
Selected Answer: D
In PRINCE2, the Project Board uses the 'Directing a Project' process to respond to an exception report. If a stage or project tolerance is forecast to be exceeded, an exception report is raised by the Project Manager, and the Project Board must decide on the appropriate course of action. The 'Directing a Project' process enables the Project Board to provide guidance, make decisions, and take corrective actions as needed when exceptions occur.
upvoted 2 times
...
9f54d15
4 months, 1 week ago
No, it is D. This process provides the project board with key decision points about whether to continue with the project or stop it. When an exception report is received, it’s the project board’s responsibility to review it and decide on the next steps.
upvoted 1 times
...
El_Cabron
1 year, 3 months ago
Selected Answer: B
The Managing a Stage Boundary process is where the project board receives and reviews the exception report.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...