B is correct;
Why other options are not suitable:
A. Controlling a stage: This process is about the project manager's activities within a stage, not the project board's response to exceptions.
C. Managing product delivery: This focuses on the creation of products, not on handling exceptions.
D. Directing a project: This is about the project board's overall direction and decision-making, but the specific process for handling exceptions is "managing a stage boundary."
In PRINCE2, the Project Board uses the 'Directing a Project' process to respond to an exception report. If a stage or project tolerance is forecast to be exceeded, an exception report is raised by the Project Manager, and the Project Board must decide on the appropriate course of action. The 'Directing a Project' process enables the Project Board to provide guidance, make decisions, and take corrective actions as needed when exceptions occur.
No, it is D. This process provides the project board with key decision points about whether to continue with the project or stop it. When an exception report is received, it’s the project board’s responsibility to review it and decide on the next steps.
The Managing a Stage Boundary process is where the project board receives and reviews the exception report.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
2 weeks, 1 day agoKjennset
1 month ago9f54d15
4 months, 1 week agoEl_Cabron
1 year, 3 months ago