exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 452 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 452
Topic #: 1
[All PRINCE2-Foundation Questions]

In which process is the work to be done assigned to a team manager?

  • A. Directing a project
  • B. Managing a stage boundary
  • C. Controlling a stage
  • D. Managing product delivery
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Examcollectorthanos
2 weeks, 1 day ago
C is correct; Why the other options are less suitable: A. Directing a project: This process is about the project board's overall guidance and authorization, not the detailed assignment of work within a stage. B. Managing a stage boundary: This process focuses on the transition between stages, not the assignment of work within a stage. D. Managing product delivery: This process is about accepting completed products from teams, not the initial assignment of the work.
upvoted 1 times
...
Kjennset
1 month ago
Selected Answer: C
In PRINCE2, the 'Controlling a Stage' process is where the Project Manager assigns work to a Team Manager through work packages. This process involves authorizing and monitoring the progress of work packages, ensuring that each team knows their responsibilities and the requirements for delivery. The Project Manager maintains control over the stage's activities, making sure that work is carried out as planned while tracking progress and managing any issues that arise.
upvoted 1 times
...
9f54d15
4 months, 1 week ago
C is correct. Activities https://prince2.wiki/processes/controlling-a-stage/ Authorize a Work Package – Assign and agree with the Team Manager.
upvoted 1 times
...
prolet
1 year ago
Selected Answer: C
During Controlling a stage process the work to be done is assigned, as within the Managing product delivery the assigned work is executed.
upvoted 2 times
...
El_Cabron
1 year, 3 months ago
Selected Answer: D
The answer is clearly D. Examtopics, where do you get these answers??
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...