The Business Development Director is the senior user. She has agreed a plan for post-project benefit reviews as part of the 'evaluate the project' activity. Is this an appropriate application of the 'closing a project' process, and why?
A.
Yes, because there should be a review of the successes and failures of the project, with recommendations for future projects to consider
B.
Yes, because there should be an assessment of the benefits achieved compared with those defined in the business case
C.
No, because the senior user should check how benefits of operational products win be measured in the 'hand over products' activity
D.
No, because it is the executive that should approve the follow-on action recommendations identified by the project manager
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ravi_aws
1 year, 9 months ago