Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2 Agile Foundation topic 1 question 24 discussion

Actual exam question from PRINCE2's PRINCE2 Agile Foundation
Question #: 24
Topic #: 1
[All PRINCE2 Agile Foundation Questions]

What information is NOT typically displayed on a burn chart?

  • A. Effort remaining
  • B. Definition of 'ready'
  • C. Actual amount of work done
  • D. Amount of time elapsed
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://worldofagile.com/blog/burn-up-chart-2/

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Esmee93
1 month, 2 weeks ago
B is correct 4.2.1 Burn chart: "A technique for showing progress (e.g. such as with a timebox), where work that is completed and work still to do are shown with one or more lines that are updated regularly or daily."
upvoted 1 times
...
SD1978
5 months, 1 week ago
Selected Answer: B
Answer is B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...