Voted C;
Why the other options are not correct:
A. Gathering user inputs: This might be part of defining quality expectations, but it's not the specific step where the project manager reviews the project product description for detailed requirements.
B. Accepting products: This happens later in the project, during product delivery.
D. Controlling quality: This involves the actual activities of checking and verifying the quality of products, not the initial definition of the quality management approach.
In the quality management technique, the project manager reviews the project product description during the step of gathering user inputs. This step involves collecting detailed requirements from users or stakeholders to ensure that the project products meet their needs and expectations. The project product description outlines these requirements, making it essential for the project manager to refer to it during this phase.
In PRINCE2, the project manager reviews the project product description in "Describing the quality management approach" to clarify requirements and ensure stakeholder expectations are documented. This sets the foundation for quality assurance and control throughout the project.
C. Describing the quality management approach.
During this step, the project manager establishes how quality will be managed throughout the project, which includes defining detailed requirements for each product to ensure they meet the desired quality standards.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos