A is correct. Why the other options are less suitable:
B. Starting up a project: This process focuses on the initial setup of the project, before the detailed planning of the work.
C. Controlling a stage: This process is about managing the work within a stage, not the initial definition and planning of the major products.
D. Managing product delivery: This process is about the detailed delivery of specific products within a stage, not the overall planning of the major products.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
5 months, 4 weeks ago