The correct answer is: D. report to the project board and
Explanation:
In PRINCE2, Project Assurance is the responsibility of the Project Board, and assurance personnel:
• Are independent of the Project Manager.
• Report directly to the Project Board.
• Provide objective oversight on aspects like business, user, and supplier assurance.
They do not report to the Project Manager or act under their direction — maintaining independence is key to their role.
i think it would be D. Project assurance is independent of the project management team and should report directly to the project board. BUT whatever findings results is also comuunicated to the project manager. Project assurance does not support the project manager as it is a role or the Project support which is part of the project team.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Kjennset
2 days, 14 hours agoa2476d0
2 months, 1 week ago