The correct answer is: A. Raise an off-specification
Explanation:
When a product cannot meet the agreed quality criteria (as described in the Product Description), the correct first action for the Project Manager is to:
🔹 Raise an off-specification
This tells the Project Board that something will be delivered differently than agreed — or not delivered at all — unless action is taken.