The project is in stage 5, and the project manager is demobilizing the project. The new biofuel system was installed correctly in stage 3 and fully tested in stage 4. However, the operations team is not sure whether it will function as planned long-term and deliver the City's sustainability targets.
In which activity of the ‘closing a project’ process should the project manager address this concern, and why?
a4d74be
1 month, 2 weeks ago