Exam PRINCE2-Practitioner topic 5 question 52 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner
Question #: 52
Topic #: 5
[All PRINCE2-Practitioner Questions]

The Sales Director would like to add a new company logo to the 'marketing material'. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 3 days and cost £900. The stage 2 cost tolerance of +£1.000 has not been used. The change budget of £500 has not been used.
Which option describes how this change should be funded?

  • A. £400 of the stage 2 cost tolerance and the £500 change budget should be used.
  • B. £900 needed for the change should be taken from the stage 2 cost tolerance.
  • C. £900 of additional funding will need to be requested to pay for the change.
  • D. £400 will need to be requested in addition to the £500 change budget.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Heidi20
1 month, 1 week ago
Selected Answer: D
The answer is D. We definitely need to use the change budget which is what it is for, and we cannot use stage cost for change. So D. Also edition 6 has the same question and the answer there is D.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.