Exam PRINCE2-Foundation topic 1 question 100 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 100
Topic #: 1
[All PRINCE2-Foundation Questions]

Which statement applies to Stage Plans?

  • A. Always have the same duration as the Project Plan
  • B. Are produced at the same time as the Project Initiation Documentation
  • C. Assist the Project Manager in the day-to-day running and control of the project
  • D. Provide a baseline against which the Project Board monitor overall progress
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rahuludayabhanu
2 months ago
Selected Answer: C
C. Assist the Project Manager in the day-to-day running and control of the project Stage Plans are created for each management stage and are used by the Project Manager to manage and control the specific stage. They provide detailed plans for the stage, enabling the Project Manager to monitor and control progress.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...