Explanation:
The Communication Management Approach in PRINCE2:
Describes how communication will be planned and controlled within the project
Specifies how the project will engage with stakeholders, including corporate, programme management, or the customer
Defines what information will be communicated, to whom, how often, and by what method
This ensures that the right stakeholders are kept informed and engaged throughout the project.
The product that describes the method the project will use to engage with corporate, programme management, or the customer is the B. Communication management approach.
Here's why:
Communication is Key: Effective communication is essential for any project, especially when dealing with stakeholders at different levels (corporate, programme, customer). A communication management approach provides a structured way to handle this.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
johnzoids
Highly Voted 5 years agoKing_Laps
Highly Voted 2 years, 9 months agomsdelima81
Most Recent 1 month, 1 week agoExamcollectorthanos
7 months, 4 weeks agogauthier59
7 months, 4 weeks agoAtito
10 months, 2 weeks agothecitrozz
2 years, 2 months agoMehan
4 years, 5 months agoShanise
4 years, 10 months agoLenlenlen
4 years, 11 months agoVikce
4 years, 12 months ago