Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2-Practitioner topic 7 question 3 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner
Question #: 3
Topic #: 7
[All PRINCE2-Practitioner Questions]

If the Project Board are too busy to authorize all change requests themselves they can appoint?

  • A. A Change Authority
  • B. A Change Board
  • C. A Change Committee
  • D. A Change Budget
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Ciluba
Highly Voted 3 years, 4 months ago
Should be A
upvoted 8 times
...
Chickey
Highly Voted 3 years, 10 months ago
Answer should be A - see brochure page 142, 11.3.5
upvoted 6 times
...
Capstein_1
Most Recent 2 months ago
Change Authority can be called Change Committee.
upvoted 1 times
...
ravi_aws
7 months ago
A Change Authority
upvoted 1 times
...
SantiagoAregentina
7 months, 3 weeks ago
Selected Answer: A
A. Ref 11.3.5
upvoted 2 times
...
GSD547
2 years ago
Answer is A - clearly states this in delegating to a Change Authority (Ch 11.3.5).
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...