How should the Team Manager report that tolerances are forecast to be exceeded?

  • A. Create an Exception Report
  • B. Create a Highlight Report
  • C. Raise an issue
  • D. Grant a concession
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rahuludayabhanu
2 months ago
Selected Answer: A
A. Create an Exception Report When tolerances are forecast to be exceeded, the Team Manager should report this to the Project Manager by creating an Exception Report. This report alerts the Project Manager to the potential deviation from agreed tolerances, allowing for corrective action to be taken.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...