B. Review how well the project performed against the Project Initiation Documentation used to authorize it
Explanation: The purpose of an End Project Report in PRINCE2 is to review the project's performance against its original objectives, as outlined in the Project Initiation Documentation (PID). It assesses whether the project delivered its intended outcomes, benefits, and objectives.