Which is a purpose of an End Project Report?

  • A. Identify individuals or groups that need to be told that the project is coming to an end
  • B. Review how well the project performed against the Project Initiation Documentation used to authorize it
  • C. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
  • D. Ensure that key project information is archived and made secure
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rahuludayabhanu
2 months ago
Selected Answer: B
B. Review how well the project performed against the Project Initiation Documentation used to authorize it Explanation: The purpose of an End Project Report in PRINCE2 is to review the project's performance against its original objectives, as outlined in the Project Initiation Documentation (PID). It assesses whether the project delivered its intended outcomes, benefits, and objectives.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...