BUSINESS CASE -
Learn-it's annual business plan identified the likely costs and potential benefits of delivering the Health and Safety Training Project.
The project board has decided to delay any further development of the business case until the initiation stage, when there will be a better understanding of the scope and how it will be delivered incrementally
Is this an appropriate approach to managing the business case, and why?