Question #: 10
Topic #: 5
[All PRINCE2-Practitioner Questions]

BUSINESS CASE -
Learn-it's annual business plan identified the likely costs and potential benefits of delivering the Health and Safety Training Project.
The project board has decided to delay any further development of the business case until the initiation stage, when there will be a better understanding of the scope and how it will be delivered incrementally
Is this an appropriate approach to managing the business case, and why?

  • A. Yes, because Learn-it’s business plan provides sufficient initial justification.
  • B. Yes, because the project is being delivered incrementally.
  • C. No, because even simple projects require business justification
  • D. No, because an ‘outline business case’ should be created during the ‘starting up a project’ process.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...