A.9.2 (Prince2 guide) Off-specifications Listing any missing products or products that do not meet the original requirements,
and confirmation of any concessions granted
According to A.8.2 Composition, where mentioned about Off-specifications: "Listing any missing products or products that do not meet the original requirements, and confirmation of any concessions granted"
in a glossary also given a description for off-specification - Something that should be provided by the project, but currently is not (or is forecast not to be) . It might be a missing product or a product not meeting its specifications.
It looks A is a correct answer
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Nugi
2 years, 9 months agoMartin77
3 years agoDS001
3 years agoMehan
3 years, 3 months agosohrabiani
3 years, 6 months agoPetza
3 years, 8 months agoGetRaj
3 years, 8 months ago