DIRECTING A PROJECT -
During stage 2, an external marketing company developed the ‘marketing materials’. However, the materials did not meet the corporate standards that were supplied with the contract. The marketing company has agreed to make corrections at their own cost during stage 3. There is no impact on project tolerance. Although the work planned for stage 2 has not been completed, the project manager has recommended in the end stage report that stage 2 should finish as planned. In addition, the corrective action and a further review have been planned to take place in stage 3. This will not impact the work of stage 3
Is it appropriate for the project board to agree to the recommendation without an exception plan, and why?
Acmk
2 months ago