Question #: 86
Topic #: 5
[All PRINCE2-Practitioner Questions]

The following entry has been recorded in the issue register:
“It will be more difficult to ensure the security of the construction site due to its size. As a result, there may be unauthorized access to the site, leading to high levels of theft."
Is this an appropriate application of the ‘issues’ practice, and why?

  • A. Yes, because the project management team should be concerned about security on the site
  • B. Yes, because the project management team should consider the impact of the thefts on the project budget
  • C. No, because the project management team should record these thefts as a threat, rather than an issue
  • D. No, because the project management team should focus on the important issues
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sam_femi
1 week, 5 days ago
Selected Answer: C
The scenario describes something that might happen in the future, not something that has already happened. Therefore, it is not an issue, but a risk specifically a threat (a negative risk). This should be recorded in the risk register, not the issue register.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...