The project is in the ‘controlling a stage’ process in stage 3. The site preparation work package is progressing well and the team manager has reported that several site inspections have taken place and that there are more planned for the coming weeks. However, these inspections have not been recorded as ‘complete’ in the quality register.
As a result, the project manager calls the team manager to discuss what inspections have taken place and it becomes clear that the team manager has simply not updated the quality register. Therefore, the project manager updates the quality register to reflect the successful completion of these inspections and can now update the stage plan to show successful completion of the inspected products.
During which activity of the ‘controlling a stage’ process should the project manager take these actions?