exam questions

Exam PRINCE2-Practitioner All Questions

View all questions & answers for the PRINCE2-Practitioner exam

Exam PRINCE2-Practitioner topic 5 question 99 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner
Question #: 99
Topic #: 5
[All PRINCE2-Practitioner Questions]

The project is in the ‘controlling a stage’ process in stage 3. The site preparation work package is progressing well and the team manager has reported that several site inspections have taken place and that there are more planned for the coming weeks. However, these inspections have not been recorded as ‘complete’ in the quality register.
As a result, the project manager calls the team manager to discuss what inspections have taken place and it becomes clear that the team manager has simply not updated the quality register. Therefore, the project manager updates the quality register to reflect the successful completion of these inspections and can now update the stage plan to show successful completion of the inspected products.
During which activity of the ‘controlling a stage’ process should the project manager take these actions?

  • A. Evaluate work package status
  • B. Receive completed work package
  • C. Evaluate stage status
  • D. Report highlights
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...