Exam PRINCE2-Practitioner Edition 6 topic 17 question 6 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 6
Topic #: 17
[All PRINCE2-Practitioner Edition 6 Questions]

Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

  • A. Issue Register
  • B. Follow-on action recommendations
  • C. Lessons Report
  • D. Risk Register
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...