During the 'update the project plan' activity at the end of stage 3, the project manager identified that any delay in completing the 'delivered pilot courses' could lead to a delay in the 'finalized materials'. The project manager noted this information in the daily log immediately, with a note to transfer it to the appropriate record when it was accessible.
Which theme is being applied?