exam questions

Exam PRINCE2-Re-Registration All Questions

View all questions & answers for the PRINCE2-Re-Registration exam

Exam PRINCE2-Re-Registration topic 1 question 74 discussion

Actual exam question from PRINCE2's PRINCE2-Re-Registration
Question #: 74
Topic #: 1
[All PRINCE2-Re-Registration Questions]

Which of the following is the Business Case used for during the Managing a Stage Boundary process?

  • A. Enable the Project Board to decide whether or not to authorize the project
  • B. Justify the continuing viability of the project
  • C. Enable the Project Board to decide whether or not to authorize project closure
  • D. Justify the initiation of a project
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...