The correct answer is: C. Capture any threats or opportunities that might have an impact on a stage
Explanation:
Threats and opportunities are considered risks, not issues, and are therefore recorded in the Risk Register, not the Issue Register.
The Issue Register is used to log and manage issues, which PRINCE2 defines as events that have already happened and require management attention. These include:
• Off-specifications (e.g. a product not meeting agreed requirements)
• Requests for change
• General problems or concerns
Problems identified when authorizing a Work Package are typically dealt with before the Work Package is authorized. Any such problems would need to be resolved or escalated before the Work Package proceeds. These are more relevant to Work Package management or quality controls, not the Issue Register directly.
problems identified when authorizing a Work Package would typically be handled through the Work Package documentation and the Checkpoint Reports rather than the Issue Register.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CoffeeOD
Highly Voted 2 years agoKjennset
Most Recent 1 month, 4 weeks agorahuludayabhanu
2 months agoChi22
3 months agoIsabaut
7 months, 2 weeks agomissmanou
9 months, 2 weeks ago