This one is tricky.
D is wrong because the directing a project process starts on completion of the starting up a project process and is triggered by the request(!), not completion, to initiate a project.
Therefore A is correct: The directing a project process provides a mechanism for the project board to meet its responsibility for ensuring that there is continued business justification without being overburdened by project activity.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Jasonbahr
Highly Voted 3 years, 6 months agoa2d1fd1
Most Recent 6 months, 3 weeks ago[Removed]