Question #: 312
Topic #: 1
[All PRINCE2-Foundation Questions]

Why are projects divided into management stages?

  • A. To ensure the justification for the project is recorded and approved
  • B. To help the project board to assess a project's ongoing viability
  • C. To delegate authority for delivering the products to the team manager
  • D. To focus on the delivery of products to defined quality requirements
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
https://www.greycampus.com/opencampus/prince-2-practitioner/concept-of-management-stages-in-prince2

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mirin000
1 year, 9 months ago
Selected Answer: B
B is correct
upvoted 3 times
...
AliSami
2 years ago
B is the correct answer
upvoted 2 times
...
Martin77
2 years, 11 months ago
B is correct
upvoted 2 times
...
theotenis
2 years, 11 months ago
The answer should be B. Even from the URL provided in the answer.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...