Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2-Foundation topic 1 question 40 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 40
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a purpose of the Initiating a Project process?

  • A. Decide if it is worthwhile to initiate a project
  • B. Decide on the project approach
  • C. Establish solid foundations for a project
  • D. Identify the number of Work Packages required
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
a2d1fd1
3 weeks ago
Selected Answer: C
C is correct.
upvoted 1 times
...
Isabaut
1 year, 11 months ago
Selected Answer: C
Correct
upvoted 1 times
...
matters
2 years, 8 months ago
Ref 16.1 - The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project product before committing to a significant spend.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...