Question #: 141
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is an objective of the Starting up a Project process?

  • A. Identify who will be responsible for creating the Project Plan
  • B. Agree how the project will be monitored and controlled after initiation
  • C. Authorize the Project Manager to proceed with the initiation stage
  • D. Agree how issues and changes will be identified, assessed and controlled
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Chucky2
Highly Voted 1 year, 5 months ago
Selected Answer: A
A is correct The objective of starting up a project process is to ensure that there is a business justification for initiating the project. Sufficient information is available to define and confirm the scope of the project. The various ways that a project can be delivered are evaluated and a project approach is selected. Individuals are appointed who will undertake the work required in project initiation and all will take significant project management roles in the project.
upvoted 5 times
...
aac220a
Most Recent 1 day, 17 hours ago
Selected Answer: C
C is correct.
upvoted 1 times
...
Kjennset
1 day, 17 hours ago
Selected Answer: C
The correct answer is: C. Authorize the Project Manager to proceed with the initiation stage Explanation: The Starting up a Project process in PRINCE2 is focused on ensuring that there is a clear foundation for the project before formally starting the Initiation Stage. The main objective here is to confirm that the project has the necessary resources, authority, and planning to move forward. One of its key tasks is to authorize the Project Manager to proceed with the Initiation Stage, where the detailed planning and establishment of the project will take place.
upvoted 1 times
...
dandandu1986
10 months ago
C. 14.2 individuals are appointed who will undertake the work required in project initiation and/or will take significant project management roles in the project
upvoted 1 times
...
MrMooMooBee
1 year, 3 months ago
Authorisation of the initiation stages is Directing a Project so C isn't correct.
upvoted 1 times
...
Risto83
1 year, 4 months ago
A "Authorize" is in directing a project.
upvoted 1 times
...
jj0097
1 year, 10 months ago
Selected Answer: C
C is good
upvoted 1 times
...
peppe
2 years, 6 months ago
The project plan is created during the initiating a project process and updated towards the end of each management stage during the managing a stage boundary process.
upvoted 3 times
...
peppe
2 years, 6 months ago
i would say C
upvoted 2 times
...
kal5
2 years, 6 months ago
Referens for this answer appriciated
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago