A is correct
The objective of starting up a project process is to ensure that there is a business justification for initiating the project. Sufficient information is available to define and confirm the scope of the project. The various ways that a project can be delivered are evaluated and a project approach is selected. Individuals are appointed who will undertake the work required in project initiation and all will take significant project management roles in the project.
The correct answer is: C. Authorize the Project Manager to proceed with the initiation stage
Explanation:
The Starting up a Project process in PRINCE2 is focused on ensuring that there is a clear foundation for the project before formally starting the Initiation Stage. The main objective here is to confirm that the project has the necessary resources, authority, and planning to move forward.
One of its key tasks is to authorize the Project Manager to proceed with the Initiation Stage, where the detailed planning and establishment of the project will take place.
C.
14.2 individuals are appointed who will undertake the work required in project initiation and/or will take significant project management roles in the project
The project plan is created during the initiating a project process and updated towards the end of each management stage during the managing a stage boundary process.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Chucky2
Highly Voted 1 year, 5 months agoaac220a
Most Recent 1 day, 17 hours agoKjennset
1 day, 17 hours agodandandu1986
10 months agoMrMooMooBee
1 year, 3 months agoRisto83
1 year, 4 months agojj0097
1 year, 10 months agopeppe
2 years, 6 months agopeppe
2 years, 6 months agokal5
2 years, 6 months ago