The correct answer must be MB (Managing a stage boundary):
Stage boundaries enables the team to look both forwards and backwards. Looking backwards, it helps the team understand:
How did we do?
How much was delivered?
To what quality?
What benefit was delivered?
Did the process work well?
Release reviews and retrospectives?
In 19.3.3
"Reporting of progress at the end of a sprint or a release is done via the sprint or
release review and the optional product demo, which provides the opportunity to
discuss planned features which were not delivered or those that were but were not
originally planned for the release."
so it seems that release review is held during Controlling a Stage, so maybe the correct answer is A.
upvoted 1 times
...
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.