Which role should identify whether a project's management products need to be tailored?

  • A. Team manager
  • B. Executive
  • C. Senior user
  • D. Project manager
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
Highly Voted 2 years, 6 months ago
It should be D: Tailoring requires the project board and the project manager to make proactive choices and decisions on how PRINCE2 will be applied. 3.7
upvoted 6 times
...
skillfulsatellite
Most Recent 1 week, 5 days ago
Selected Answer: D
The Project Manager is responsible for tailoring the PRINCE2 approach to suit the specific needs of the project
upvoted 1 times
...
Examcollectorthanos
2 weeks, 5 days ago
D is correct; Why the other options are not correct: A. Team manager: The team manager focuses on managing a team to deliver a work package, not on tailoring the overall project management approach. B. Executive: The executive is accountable for the project's success but doesn't typically get involved in the detailed tailoring of management products. C. Senior user: The senior user represents the interests of the users but doesn't usually have the expertise to determine the need for tailoring PRINCE2 products.
upvoted 1 times
...
Kjennset
1 month ago
Selected Answer: D
The Project Manager is responsible for identifying whether the project’s management products need to be tailored to fit the specific context and requirements of the project. This involves assessing the needs of the project, the complexity, and the scale of the work to determine the appropriate level of documentation and management processes required. Tailoring ensures that the PRINCE2 methodology is applied effectively and efficiently to suit the particular project environment.
upvoted 1 times
...
bes_i
4 months, 1 week ago
Selected Answer: D
D. Project Manager The Project Manager is responsible for tailoring PRINCE2 to suit the specific needs of the project. This includes determining how the management products, processes, and themes will be adjusted to fit the project's size, complexity, and risk level. The Project Manager ensures that the project management approach is appropriate and effective for the particular circumstances of the project.
upvoted 1 times
...
Lynl
2 years, 7 months ago
Answer should be D
upvoted 3 times
...
KANDUUR
2 years, 10 months ago
Not sure that this is a correct answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...