Which is a minimum requirement for applying the 'organization' theme?

  • A. To provide unified direction to the project through a democratic project board
  • B. To delegate responsibility for managing product delivery to team managers
  • C. To allocate a separate group to carry out project support tasks
  • D. To document the rules for delegating change authority responsibilities, if required
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rahuludayabhanu
3 days, 2 hours ago
Selected Answer: B
The min requirement is to establish a clear structure of roles and responsibilities. Among the options provided, the most relevant minimum requirement is: B. To delegate responsibility for managing product delivery to team managers This option reflects the need to have a clear delegation of responsibilities within the project organization, which is a fundamental aspect of the 'organization' theme. While option D touches on documenting delegation rules, which is crucial for clarity and effective governance, it is more closely related to the 'Change' theme rather than the core 'Organization' theme requirements.
upvoted 1 times
...
Examcollectorthanos
6 months ago
D; The other options are not minimum requirements: A. To provide unified direction to the project through a democratic project board: While a unified direction is important, a democratic project board is not mandatory. B. To delegate responsibility for managing product delivery to team managers: This is usually the case, but not always a strict requirement. C. To allocate a separate group to carry out project support tasks: Project support can be provided in various ways, not necessarily by a separate group
upvoted 1 times
...
KANDUUR
3 years, 3 months ago
7.2 correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago