This is confusing; Question #30
Which is a purpose of the 'directing a project' process?
C. To delegate day to day management of the project to the project manager
The objectives of the Directing a Project process are to provide authority (to make a decision)
To initiate the project (allow the Initiating a Project process to start).
To deliver the project’s products (start the delivery stages).
To close the project (when the Closing a Project process is done).
Provide direction and control during the project.
Be the interface to Corporate / Programme Management.
Ensure that post-project benefits will be reviewed.
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 month agoExamcollectorthanos
1 month agoAnnie7799666
2 years, 6 months ago