Exam PRINCE2-Foundation topic 1 question 31 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 31
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is an objective of the Directing a Project process?

  • A. Create and authorize the project mandate
  • B. Provide management control and direction
  • C. Control the day-to-day running of the project
  • D. Provide accurate progress information to the Project Manager
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
This is confusing; Question #30 Which is a purpose of the 'directing a project' process? C. To delegate day to day management of the project to the project manager
upvoted 1 times
I say C As per previous questions
upvoted 1 times
...
...
Annie7799666
2 years, 6 months ago
The objectives of the Directing a Project process are to provide authority (to make a decision) To initiate the project (allow the Initiating a Project process to start). To deliver the project’s products (start the delivery stages). To close the project (when the Closing a Project process is done). Provide direction and control during the project. Be the interface to Corporate / Programme Management. Ensure that post-project benefits will be reviewed.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...