B is correct. After an issue has been identified and captured, there needs to be a controlled process for assessing the issue and determining what action to take in response. A prerequisite of effective issue and change control is to define a way of creating baselines of products and allowing appropriately controlled changes to those baselines.
The Change theme aims to develop a reliable change management approach, to enable the Project Manager to deal with each potential change, while maintaining the stability and security of the project.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 month agotest235
11 months, 3 weeks agoomande
1 year, 3 months agoKeybe
1 year, 4 months agoIsabaut
2 years, 6 months ago