If drives need to be relocated within an array for an XFORM upgrade, when should this be completed?

  • A. During the upgrade
  • B. After upgrade is completed
  • C. The following day
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
5b0296b
1 month ago
Selected Answer: A
The physical relocation of DFMs from the old array to the new FlashArray, including the necessary data evacuation and one-by-one transfer, is an integral part of the non-disruptive upgrade process and is completed during the upgrade
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...