Question #: 14
Topic #: 1
[All C_TS413_2021 Questions]

You want to assign components to an equipment task list. There is no BOM assigned to the equipment.
What is the prerequisite for using the free assignment of material?

  • A. Assign the header material of a material BOM to the equipment task list header.
  • B. Assign the BOM usage for free assignment of material in Customizing.
  • C. Assign the header material of a material BOM as assembly to a task list operation.
  • D. Free assignment of material is always possible without any prerequisites.
Show Suggested Answer Hide Answer
Suggested Answer: C -
🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
a50e462
1 month, 3 weeks ago
B is the answer here. You must configure it to allow free material assignment. You don't need a material BOM to do this.
upvoted 2 times
...
sye93
3 months, 1 week ago
B is the answer
upvoted 1 times
...
Leo_FsGT
8 months ago
Selected Answer: B
To make a free material assignment, you must specify a BOM usage (generally used in Plant Maintenance) in Customizing (Control Data for Task List)
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...