Actual exam question from Scrum's PSM I
Question #: 12
Topic #: 1
[All PSM I Questions]

What is the purpose of a Sprint Review?

  • A. To take time to judge the validity of the project.
  • B. To inspect the product Increment with the stakeholders and collect feedback on next steps.
  • C. To review the Scrum Team's activities and processes during the Sprint.
  • D. To build team sprint.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
alb81
1 week, 5 days ago
Selected Answer: B
B is the correct one
upvoted 1 times
...
alb81
1 week, 5 days ago
Selected Answer: B
B is the coct one
upvoted 1 times
...
okayhey
8 months, 2 weeks ago
Selected Answer: B
Correct, increment is presented (not released, that's up to discretion of PO)
upvoted 1 times
...
Djedjig
10 months ago
B is correct
upvoted 1 times
...
Jyoti1010
1 year, 2 months ago
Option B
upvoted 2 times
...
Mi_Windsor
1 year, 4 months ago
B is the correct answer
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...