As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)
A.
Recruit additional Development Team members before the work can begin.
B.
The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress.
C.
Cancel the Sprint.
D.
Remove or change selected Product Backlog items.
E.
The Development Team works overtime during this Sprint.
This section is not available anymore. Please use the main Exam Page.PSM I Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
DinithiB
Highly Voted 4 years, 10 months agoDjedjig
Most Recent 11 months agoIssam_KHELIL
1 year, 3 months agoJyoti1010
1 year, 3 months agoMi_Windsor
1 year, 5 months agoAtanu_M
3 years, 9 months ago