Sprint burndown charts are an efficient tracking tool, because they show:

  • A. An estimate of the total work remaining for the Sprint.
  • B. How much effort has gone into a Sprint.
  • C. How many hours have been worked by each Development Team member.
  • D. How many Product Backlog items remain.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://jazz.net/agile-alm-scrum-practices/core.mgmt.common.extend_supp_scrum-ibm/workproducts/ sprint_burndown_chart_8BBCD86F.html#:~:text=A%20sprint%20burn%20down%20chart,work%20remaining%20for%20the%20Sprint

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...