Hello All.
I have a question: On which sprint we have to do this integration ?
Supposing that we have 3 teams: A, B and C. And knowing that each team works on a project that is a part of whole system solution. And each team has its own sprint lenght ans characteristics. So when the integration can be done? note that for each project has two types of features: story depending only to this project or story dpending on another project (other team and here where we can have this issue?)
Hi.
Purpose of the sprint is to produce a working increment so option B is correct, If we would only integrate dependencies how would we have a working product or increment?
B. Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.
upvoted 4 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Vicnif
Highly Voted 3 years, 8 months agowax_gibbous
Most Recent 1 month agofembad
3 months, 1 week agoMi_Windsor
4 months, 2 weeks agoUmaPradeep
5 months, 2 weeks agoqwerttyy
2 years, 11 months agoadendane
3 years, 1 month agoaguchux
3 months agoRavindra77
4 months, 3 weeks agoJBento
3 years, 2 months agojcesarguedes
3 years, 8 months agoKhaled123
3 years, 8 months agogentle
3 years, 8 months ago