Which does a self-organizing Development Team choose?

  • A. Sprint length.
  • B. How to best accomplish its work.
  • C. Stakeholders for the Sprint Review.
  • D. When to release, based on its progress.
  • E. Product Backlog ordering.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.scrum.org/resources/blog/about-self-organizing-teams#:~:text=%22Self%2Dorganizing%20teams%20choose%20how,and%20manage%
20their%20own%20work.%22

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...