One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (Choose two.)

  • A. A shared understanding of the most important work to be undertaken next to achieve the best possible progress toward the Sprint goal.
  • B. An update of completed tasks and of the remaining work so the Scrum Master can plan the next day.
  • C. A status report for the upper management indicating what each individual has done, will be doing, and what is impending him/her.
  • D. An updated Scrum board to make Sprint progress transparent for the stakeholders.
  • E. Identification of impediments that may prevent the Developers from achieving the Sprint Goal.
Show Suggested Answer Hide Answer
Suggested Answer: AE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...