Exam PSM I topic 1 question 168 discussion

Actual exam question from Scrum's PSM I
Question #: 168
Topic #: 1
[All PSM I Questions]

When many Development Teams are working on a single product, what best describes the definition of `Done`? (Choose the best answer.)

  • A. Each Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.
  • B. It depends.
  • C. Each Development Team uses its own but must make their definition clear to all other teams so the differences are known.
  • D. All Development Teams must have a definition of ג€Doneג€ that makes their combined work potentially releasable.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...