What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which agile practices to apply? (Choose two.)
A.
Involve the complete Scrum Team in making a decision.
B.
Use coaching techniques; such as open questions and active listening.
C.
Ask an external agile coach what they recommend.
D.
Ask team members to take the issue up with to the company's Human Resources department.