Question #: 44
Topic #: 1
[All PSPO I Questions]

What is the responsibility of the Product Owner in crafting the Sprint Goal? (Choose the best answer.)

  • A. The Product Owner defines the scope for a Sprint and therefore also the Sprint Goal.
  • B. The Product Owner must work with stakeholders to set each Sprint's Goal.
  • C. The Product Owner should come to Sprint Planning with a business objective in mind and work with the Developers to craft the Sprint Goal.
  • D. The Product Owner has no responsibility for the Sprint Goal. It is the sole responsibility of the Developers.
  • E. The Product Owner cannot attend Sprint Planning without having documented the Sprint Goal in advance.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...