What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning? (Choose the best answer.)

  • A. Sprint Planning is canceled so refinement can be done first.
  • B. The Scrum Master should not allow this to happen. Look for a new Scrum Master and restart the Sprint.
  • C. Nothing in particular.
  • D. The Product Owner should select the Sprint Goal for the Scrum Team so that work can begin.
  • E. The Developers will find it difficult to create a Sprint forecast they are confident they can meet.
Show Suggested Answer Hide Answer
Suggested Answer: E 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...