exam questions

Exam CIS-PPM All Questions

View all questions & answers for the CIS-PPM exam

Exam CIS-PPM topic 1 question 67 discussion

Actual exam question from ServiceNow's CIS-PPM
Question #: 67
Topic #: 1
[All CIS-PPM Questions]

Can an it_project_manager convert a task to a milestone?

  • A. Yes, it must be manually done from the project record.
  • B. Yes, from the planning console right-click a task and select convert to milestone.
  • C. No, the task must be deleted and re-created.
  • D. No, this can only be done by an admin.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
220052
8 months ago
Selected Answer: B
[Convert a task to milestone] Right-click a task and select Convert to milestone. https://docs.servicenow.com/bundle/utah-it-business-management/page/product/project-management/reference/r_PlanningConsoleTasks.html#r_PlanningConsoleTasks__row_convert_to_milestone
upvoted 1 times
...
stophs
11 months, 3 weeks ago
Selected Answer: B
B IS CORRECT https://docs.servicenow.com/en-US/bundle/utah-it-business-management/page/product/project-management/task/t_CreateMilestones.html
upvoted 2 times
...
1307199725
1 year ago
Selected Answer: B
B is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago